Hydropower Project Development Cycle

 

Task

Private

Public

1

Site identification and selection

2

Carry out reconnaissance study (establish feasibility of scheme)

3

Apply for exclusive rights to site; Letter of Interest (LOI) issued

4

Select foreign and/or local engineering consultants and carry out bankable feasibility study (FS)

5

Carry out environmental impact assessment (EIA)

6

FS/EIA approval by respective regulators

7

Tariff petition/approval (FS stage)

8

Issuance of Letter of Support (LOS)

9

Start land acquisition process (payment at FC)

10

Tender for civil construction, electrical works and electro mechanical equipment supply and installation or turnkey EPC arrangement; evaluation, selection and contract execution

11

Negotiate and execute implementation agreement(s) covering government facilities, concessions and developers’ obligations

12

Negotiate water rights and execute water use agreement

13

Finalize O&M arrangements and execute O&M contract

14

Finalize project cost and financing plans

15

Negotiate and execute power purchase agreement (PPA)

16

Submit tariff petition/seek approval (EPC stage)

17

Finalize equity arrangements; execute shareholder(s) agreement(s)

18

Finalize loan placement, syndication and execute finance documents

19

Apply/obtain relevant consents and CPs satisfaction process

20

Establish equity/sponsor support letter of credit/guarantees

21

Negotiate and sign limited recourse government guarantee securing obligations of governmental entities incl. power purchaser

22

Financial closing, unconditional availability of funds (FC)

23

Construction start

24

Testing and commissioning to satisfy construction arrangements and power purchase requirements under PPA

25

Commencement of commercial operations

26

Tariff petition/approval (Commercial operations stage)